Our super star realtor, Susan Harvey, got us a detailed list of stages for our house. The house is now on stage 7, which is “Ready for Rough Electric.” During this stage the gutters are installed, the basement windows are put in and the electric is roughly run. After the electrical is ran, an inspector from the city of Thornton will come in and inspect all the wiring, which leads into stage 8. After the inspection, the drywall will go in. Chad is particular looking forward to stage 13, which is when they put in his expensive kitchen cabinets and counter top.

If you, or anyone you know, need a good realtor, a link to our realtor, Susan Harvey, is in the link section of this blog (at right). And if anyone wants to build a house, make sure you use a realtor to do all the dirty work, you will regret it if you don't.


1. Permit (State #1)
• Permit in band.
• Temporary electrical meter set
• Stakeout complete
• Excavation complete

2. Foundation (State #2)
• Footings /Caissons complete
• Pour Foundation Wall
• Strip Foundation Wall
• Damp poof foundation complete

3. Backfill ad Slab (Stage #3)
• Foundation Drain Complete
• Water and Sewer laterals complete
• Void & Drain inspection /UGP Stalled
• Backfill/ Rough Grade/UGP
• Tamp foundation and Garage poured

4. Framing (State #4)
• Pour basement) Frame material and
• Trusses delivered
• Frame
• Frame/Electric and gas laterals

5. Ready for Ext. Trim (Stage #5)
• Frame

6. Exterior Trim and Mech. Ron as (Stage #6)
• Frame complete/Window and Ext. Trim delivered.
• Ext. Trim/ Plumb & Heat Roughs

7. Ready for Rough Electric (Stage #7)
• Exterior Trim complete/Fireplace Set
• Back-out complete/OHD installed/Gas pipe complete. Roof Dry-in/Gutters installed basement windows installed
• Roof/Rough Electric

8. 2nd Inspection complete (Stage #8)
• Roof & Rough Electric complete/Low Voltage Complete.
• Rough punch & Sweep.
• Rough Inspection.
• Insulation.

9. Isolation and Drywall Hang (Stan #9)
• Insulation map/Drywall stout
• Hang drywall /Masonry

10. Drywall Tape (Stage #1O)
• Scrap drywall! Drywall tape
• Drywall tape

11. Textured and Ready for Interior Trim (Stage #11)
• Dry wall tape
• Drywall tape/Exterior flatwork
• Texture drywall
• Texture clean/Final Grade
• Interior Trim material delivered

12. Interior Trim and Paint (Stage #12)
• Interior Trim/Grade check complete
• Interior Trim
• Paint
• Hardwood installation and Fence installed

13. Cabinets, Tops and Paint (Stage #13)
• Cabinets set
• Counter Tops installed
• Tile/Lino

14. Ready for Carpet (Sta2e #14)
• Base & Hardware installed
• Mechanical finals
• Mirrors/Shower doors/Drywall final
• Sweep & punch
• HWF sand and coat

15. Carpet and Clean, (Stne#15)
• Carpet install
• Carpet installation complete/Bump & guide
• Final Clean
• Screens and service

16. Released for Orientation (Stage #16)
• EWE coat
• Punch for final inspections
• Final inspection
• Final inspection
• CO issued
17. Home dosed (stage #17)